Author: John M. Scagnelli
Date: February 16, 2021

Partner
201-896-4100 jscagnelli@sh-law.com
The New Jersey Department of Environmental Protection (NJDEP) recently announced that it is further extending certain site remediation timeframes in light of the ongoing COVID-19 pandemic for an additional 185 days. As set forth in the NJDEP’s Notice of Rule Waiver/Modification/ Suspension (Notice), the NJDEP is also granting a one-year extension to the May 2021 Remedial Action timeframe under the Site Remediation Reform Act (SRRA).
As discussed in prior articles, the NJDEP previously extended certain timeframes for completion of remediation activities set forth in the Administrative Requirements for the Remediation of Contaminated Sites (ARRCS), N.J.A.C. 7:26C, the Technical Requirements for Site Remediation, N.J.A.C. 7:26E, and the Heating Oil Tank System Remediation Rules, N.J.A.C. 7:26F. Under the Notices of Rule Waiver/Modification/Suspension issued on April 24, 2020, and August 17, 2020, the time frames were extended for a total of 270 days.
The NJDEP’s latest Notice, dated February 1, 2021, authorizes the following extensions:
As emphasized by the NJDEP, the temporary rule modifications are limited to reporting requirements only and do not extend any timeframes for the mitigation of immediate impacts to human receptors. Additionally, entities responsible for conducting the remediation must have retained a Licensed Site Remediation Professional in order to qualify for the extension.
If you have any questions or if you would like to discuss the matter further, please contact me, John Scagnelli, or the Scarinci Hollenbeck attorney with whom you work, at 201-896-4100.
No Aspect of the advertisement has been approved by the Supreme Court. Results may vary depending on your particular facts and legal circumstances.

Developers, engineering, procurement, and construction (EPC) contractors, and equipment suppliers each play a critical role in completing a BESS project. However, when equipment costs rise, deliveries are delayed, or regulations change, determining who bears the financial consequences can become contentious. Well-drafted project agreements are essential to sound risk allocation. Key Takeaways This article is Part […]
Author: Nicholas Wall

IP infringement occurs when someone uses your intellectual property without your permission or beyond the scope of the permission you granted. Common examples of IP infringement include copying a product’s patented features or using a trademarked logo in a way that is likely to confuse consumers about the source or affiliation of goods or services. […]
Author: Michael Mietlicki

When facing public allegations of wrongdoing, companies should not let the speed of the public conversation dictate the speed of an investigation. An investigation designed to confirm a preferred narrative rather than establish the facts can create serious problems later, particularly if litigation, regulatory scrutiny, or employment claims follow. Key Takeaways When public allegations surface […]
Author: Sean M. Pena

For battery energy storage system (BESS) developers, securing equipment and site control is only part of the development equation. A project must also connect to the electric grid, and increasingly, BESS interconnection is one of the biggest sources of schedule, cost, and contractual risk. Key Takeaways This article is Part 3 of our Battery Storage […]
Author: Nicholas Wall

Director and officer liability increases sharply when a company is in financial distress. Decisions that would draw little attention in a healthy business can later be challenged by creditors, shareholders, bankruptcy trustees, and regulators as breaches of fiduciary duty, fraudulent transfers, or oversight failures. Understanding where that exposure comes from, and how to manage it, […]
Author: Michael Mietlicki

For developers pursuing battery energy storage system (BESS) projects, finding the right property is only the beginning. BESS site selection is as much a legal and transactional exercise as a real estate decision, with risk analysis central to the project’s ultimate success. Key Takeaways The core questions for BESS site selection in New York and […]
Author: Nicholas Wall
No Aspect of the advertisement has been approved by the Supreme Court. Results may vary depending on your particular facts and legal circumstances.
Consider subscribing to our Firm Insights mailing list by clicking the button below so you can keep up to date with the firm`s latest articles covering various legal topics.
Stay informed and inspired with the latest updates, insights, and events from Scarinci Hollenbeck. Our resource library provides valuable content across a range of categories to keep you connected and ahead of the curve.
Let`s get in touch!
Sign up to get the latest from the Scarinci Hollenbeck, LLC attorneys!